[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157231":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157231,817,2,"多选题","根据施工组织设计编制的设计阶段的不同，可以将施工组织设计分为（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工组织总设计",false,{"key":16,"text":17,"correct":14},"B","单位工程施工组织设计",{"key":19,"text":20,"correct":14},"C","单项工程施工组织设计",{"key":22,"text":23,"correct":24},"D","投标前施工组织设计",true,{"key":26,"text":27,"correct":24},"E","中标后施工组织设计","DE","根据施工组织设计编制的设计阶段的不同，可以将施工组织设计分为投标前施工组织设计、类似工程项目建设的经验资料。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]