[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157228":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157228,817,2,"多选题","工程变更包含（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","设计变更",true,{"key":16,"text":17,"correct":14},"B","发包入提出的变更",{"key":19,"text":20,"correct":14},"C","监理工程师提出的变更",{"key":22,"text":23,"correct":24},"D","承包人提出的变更",false,{"key":26,"text":27,"correct":24},"E","政府监督机构要求","ABC","工程变更包括设计变更、进度计划变更、施工条件变更、技术规范和标准变更、施工次序变更、工程数量变更等。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]