[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157211":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157211,817,2,"多选题","基坑挖至基底设计标高并清理后，施工单位必须会同（ ）共同进行验槽，合格后方能进行下道工序施工。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","勘察单位",true,{"key":16,"text":17,"correct":14},"B","建设单位",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":14},"D","设计单位",{"key":25,"text":26,"correct":27},"E","分包单位",false,"ABCD","基坑挖至基底设计标高并清理后，施工单位必须会同勘察单位、建设单位、监理单位、设计单位共同进行验槽，合格后方能进行下道工序施工。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]