[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157208":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157208,817,2,"多选题","下列关于模板安装与拆除的基本规定中正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","同一条拼缝上的U形卡，不宜向同一方向卡紧",true,{"key":16,"text":17,"correct":18},"B","钢楞宜采用整根杆件，接头宜错开设置，搭接长度不应小于300mm",false,{"key":20,"text":21,"correct":14},"C","模板支设时，采用预组拼方法，可以加快施工速度，提高工效和模板的安装质量，但必须具备相适应的吊装设备和有较大的拼装场地",{"key":23,"text":24,"correct":18},"D","模板拆除时，当混凝土强度大于2N\u002Fm㎡时，应先拆除侧面模板，再拆除承重模板",{"key":26,"text":27,"correct":14},"E","模板拆除的顺序和方法，应按照配板设计的规定进行，遵循先支后拆，先非承重部位，后承重部位以及自上而下的原则","ACE","钢楞宜采用整根杆件, 接头应错开设置, 搭接长度不应少于 200mm。 混凝土拆除的顺序一般是先拆非承重模板，后拆承重模板；先拆侧模板，后拆底模板。不同跨度，混凝土要求强度也不同。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]