[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1157197":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1157197,817,2,"多选题","下列关于筏形基础的基本规定的各项中，正确的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","筏形基础分为梁板式和平板式两种类型，梁板式又分为正向梁板式和反向梁板式",true,{"key":16,"text":17,"correct":18},"B","施工工艺流程为：测量放线→基坑支护→排水、降水（或隔水）→基坑开挖、验槽→混凝土垫层施工→支基础模板→钢筋绑扎→浇基础混凝土",false,{"key":20,"text":21,"correct":18},"C","回填应由两侧向中间进行，并分层夯实",{"key":23,"text":24,"correct":14},"D","当采用机械开挖时，应保留200~300mm土层由入工挖除",{"key":26,"text":27,"correct":14},"E","基础长度超过40m时，宜设置施工缝，缝宽不宜小于80Cm","ADE","筏形基础施工工艺流程测量施工→基坑支护→基坑排水、降水（或隔水）→基坑开挖、验槽→混凝土垫层施工→钢筋绑扎→基础模板安装→基础混凝土浇筑；回填应在相对的两侧或四周同时均匀进行，并分层穷实。",{"id":6,"name":31,"category":32,"favorite":33},"(标准员)基础知识","建筑工程",0]