[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156998":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1156998,817,1,"单选题","按照《建设工程安全生产管理条例》的规定，建设单位的安全责任除了向施工单位提供现场相关资料、依法办理相关批准手续、提供安全生产费用及不推销劣质材料设备外，还包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制施工现场临时用电方案的责任",false,{"key":16,"text":17,"correct":14},"B","统一协调总、分包单位安全生产的责任",{"key":19,"text":20,"correct":14},"C","要求设计单位按照强制性标准设计",{"key":22,"text":23,"correct":24},"D","对拆除工程进行备案的责任",true,"按照《建设工程安全生产管理条例》的规定，建设单位的安全责任是要向施工单位提供现场相关资料、依法办理相关批准手续、提供安全生产费用及不推销劣质材料设备、对拆除工程进行备案。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]