[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156983,817,1,"单选题","某设计单位对承接的设计任务采用了如下做法，其中符合法律规定的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","将主要设计任务交由合作单位完成",false,{"key":16,"text":17,"correct":14},"B","由其他事务所设计人员设计，图纸上使用本单位图签",{"key":19,"text":20,"correct":21},"C","将设计的现场服务委托其他单位完成",true,{"key":23,"text":24,"correct":14},"D","将全部任务转包","主要设计任务应由设计单位自己负责；禁止以其他勘察、设计单位的名义承揽工程或者允许其他单位、个人以本单位的名义承揽工程，禁止转包或者违法分包所承揽的工程。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]