[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1156943,817,1,"单选题","某工程承包单位完成了设计图纸和合同规定的施工任务，建设单位欲组织竣工验收，按照《建设工程质量管理条例》规定的工程竣工验收必备条件不包括的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","完整的技术档案和施工管理资料",true,{"key":16,"text":17,"correct":18},"B","工程使用的主要建筑材料、建筑构配件和设备的进场试验报告",false,{"key":20,"text":21,"correct":18},"C","勘察、设计、施工、工程监理等单位共同签署的质量合格文件",{"key":23,"text":24,"correct":18},"D","施工单位签署的工程保修书","工程竣工验收必备条件应有勘察、设计、施工、工程监理等单位分别签署的质量合格文件。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]