[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156903":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156903,817,1,"单选题","建设单位应当自工程竣工验收合格之日起（ ）进行竣工验收备案。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7日内",false,{"key":16,"text":17,"correct":14},"B","10日内",{"key":19,"text":20,"correct":21},"C","15日内",true,{"key":23,"text":24,"correct":14},"D","20日内","按照《建设工程质量管理条例》的规定，建设单位应当在工程竣工验收合格之日起15日内履行工程竣工验收备案手续。\\n 。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]