[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156897":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156897,817,1,"单选题","工程建设中预留保证金的比例，下列说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","全部使用政府投资的建设项目，按合同价款5％左右预留",false,{"key":16,"text":17,"correct":18},"B","部分使用政府投资的建设项目，按工程价款结算总额5％左右预留",true,{"key":20,"text":21,"correct":14},"C","社会投资项目-律按工程价款结算总额5％左右预留",{"key":23,"text":24,"correct":14},"D","社会投资项目-律按合同价款10％左右预留","全部或者部分使用政府投资的建设项目，按工程价款结算总额5%左右的比例预留保证金。社会投资项目采用预留保证金方式的，预留保证金的比例可参照执行。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]