[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156874":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156874,817,1,"单选题","施工过程中，工程监理人员认为工程施工不符合工程设计要求、施工技术标准和合同约定的，（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","要求设计单位修改设计文件",false,{"key":16,"text":17,"correct":14},"B","报告建设单位要求设计单位改正",{"key":19,"text":20,"correct":21},"C","有权要求建筑施工企业改正",true,{"key":23,"text":24,"correct":14},"D","直接要求分包商立即改正","施工过程中，工程监理人员认为工程施工不符合工程设计要求、施工技术标准和合同约定的，有权要求建筑施工企业改正。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]