[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156830":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1156830,817,1,"单选题","担任施工项目负责人的注册建造师，在所负责的工程项目竣工验收或交接手续办结前，不得变更注册到另-企业，除非该项目（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包方同意更换项目负责人",true,{"key":16,"text":17,"correct":18},"B","承包方同意更换项目负责人",false,{"key":20,"text":21,"correct":18},"C","发包方与承包方产生了合同纠纷",{"key":23,"text":24,"correct":18},"D","因不可抗力暂停施工","规定的情形：发包方与注册建造师受聘企业己解除承包合同的；发包方同意更换项目负责人的；因不可抗力等特殊情况必须更换项自负责人的。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]