[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156823":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1156823,817,1,"单选题","按照《建设工程施工合同文本》通用条款规定，工程具备隐蔽条件后，施工单位进行自检，并在隐蔽前（ ）以书面形式通知监理工程师验收。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1日",false,{"key":16,"text":17,"correct":14},"B","36小时",{"key":19,"text":20,"correct":14},"C","24小时",{"key":22,"text":23,"correct":24},"D","48小时",true,"除专用合同条款另有约定外，工程隐蔽部位经承包人自检确认具备覆盖条件的，承包人应在共同检查前48小时书面通知监理人检查，通知中应载明隐蔽检查的内容、时间和地点，并应附有自检记录和必要的检查资料。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]