[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156810":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156810,817,1,"单选题","某多层钢筋混凝土现浇框架结构施工，抗震等级为三级，主要结构钢材品种为HPB300、HRB400 E，柱筋接长采用电渣压力焊施工。根据本项目情况标准员编制了执行工程建设标准强制性条文落实计划表，见表1。请根据上述背景资料完成以下选项。 本工程一次进场HRB400E钢筋65t，则按规定至少需取样（ ）组试件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","取样方法：按照同一批量、同一规格、同一炉号、同一出厂日期、同一交货状态的钢筋，每批重量不大于60t为一检验批，进行现场见证取样；当不足60t也为一个检验批，进行现场见证取样。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]