[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156795":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1156795,817,1,"单选题","某多层钢筋混凝土现浇框架结构施工，抗震等级为三级，主要结构钢材品种为HPB300、HRB400 E，柱筋接长采用电渣压力焊施工。根据本项目情况标准员编制了执行工程建设标准强制性条文落实计划表，见表1。请根据上述背景资料完成以下选项。 工地对热轧钢筋进行重量偏差检验，按规定每批应抽取（ ）个试件。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","5",true,"钢筋取样试验取：每批抽取5个试件，先进行重量偏差检验，再取其中2个试件进行力学性能检验。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]