[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156786":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156786,817,1,"单选题","下列属于PDCA中处置的活动是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定质量控制的组织制度",false,{"key":16,"text":17,"correct":14},"B","按计划开展技术交底",{"key":19,"text":20,"correct":21},"C","对检查发现的质量问题采取措施",true,{"key":23,"text":24,"correct":14},"D","检查工程是否按计划执行","PDCA的循环：分析现状，发现问题。分析质量问题中各种影响因素。找出影响质量问题的主要原因。针对主要原因，提出解决的措施并执行。检查执行结果是否达到了预定的目标。把成功的经验总结出来，制定相应的标准。把没有解决或新出现的问题转入下一个PDCA循环去解决。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]