[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156772":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1156772,817,1,"单选题","在施工成本动态控制过程中，当对工程合同价与实际施工成本、工程款支付进行比较时，成本的计划值是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程合同价",true,{"key":16,"text":17,"correct":18},"B","实际施工成本",false,{"key":20,"text":21,"correct":18},"C","工程款支付额",{"key":23,"text":24,"correct":18},"D","施工图预算","在施工成本动态控制过程中，当对工程合同价与实际施工成本、工程款支付进行比较时，成本的计划值是工程合同价。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]