[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156771":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156771,817,1,"单选题","某工程双代号网络计划如图所示（时间单位：d），则该计划的关键线路是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①②③④⑤⑥",false,{"key":16,"text":17,"correct":14},"B","①②③④⑥",{"key":19,"text":20,"correct":21},"C","①③④⑥",true,{"key":23,"text":24,"correct":14},"D","①③⑤⑥","经计算，该网络图的计算工期为16天，关键线路为①－③－④－⑥。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]