[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156762,817,1,"单选题","项目施工过程中，为对项目目标进行动态跟踪和控制，在确定目标控制的计划值之后，首先要做的工作是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整项目目标",false,{"key":16,"text":17,"correct":14},"B","比较项目目标的实际值与计划值",{"key":19,"text":20,"correct":21},"C","收集项目目标的实际值",true,{"key":23,"text":24,"correct":14},"D","采取纠偏措施进行纠错","在施工过程中对施工进度目标进行动态跟踪和控制的工作包括：①收集施工进度实际值：②定期对施工进度的计划值和实际值进行比较：③如有偏差，采取措施进行纠偏。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]