[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156761,817,1,"单选题","编制工程项目施工组织设计时，一般将施工段的划分、施工顺序的安排列入施工组织设计的（ ）部分。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工进度计划",false,{"key":16,"text":17,"correct":14},"B","施工总平面图",{"key":19,"text":20,"correct":21},"C","施工部署和施工方案",true,{"key":23,"text":24,"correct":14},"D","工程概况","编制工程项目施工组织设计时，一般将施工段的划分、施工顺序的安排列入施工组织设计的施工部署和施工方案部分。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]