[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156759":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156759,817,1,"单选题","施工项目技术负责人每天在施工日志上对当天的施工质量和进度情况进行详细记载，属于目标动态控制过程中（ ）的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","准备阶段",false,{"key":16,"text":17,"correct":18},"B","收集项目实际值",true,{"key":20,"text":21,"correct":14},"C","进行目标计划值和实际值比较",{"key":23,"text":24,"correct":14},"D","纠偏环节","项目目标实施过程中，首先应进行的工作是收集目标的实际完成值。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]