[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156754":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1156754,817,1,"单选题","某建设工程项目的总承包商在该项目组织结构采用了线性组织结构模式，这种组织结构的特点是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","每个工作部门只接受-八上级的直接领导",true,{"key":16,"text":17,"correct":18},"B","可能有多个矛盾的指令源",false,{"key":20,"text":21,"correct":18},"C","有横向和纵向两个指令源",{"key":23,"text":24,"correct":18},"D","促进了管理专业化分工","线性组织结构是指按照纵向关系逐级安排责、权的组织方式。在线性组织结构中，每一个工作部门只有一个指令源，避免了由于矛盾的指令而影响组织系统的运行。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]