[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156752,817,1,"单选题","某建设工程施工进度计划如下图所示（时间单位：天），则该计划的计算工期是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":21},"C","23",true,{"key":23,"text":24,"correct":14},"D","25","关键路线是①—②—④—⑧—⑨—⑩。2+3+7+7+4=23天。参见教材P54.",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]