[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156747":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1156747,817,1,"单选题","有时由于各施工段的工程量不等，各施工班组的施工入数又不同，使同一施工过程在各施工段上或各施工过程在同一施工段上的流水节拍无规律性，这是需要组织（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","等节拍流水",false,{"key":16,"text":17,"correct":14},"B","成倍节拍专业流水",{"key":19,"text":20,"correct":14},"C","加快成倍节拍专业流水",{"key":22,"text":23,"correct":24},"D","无节奏专业流水",true,"有时由于各施工段的工程量不等，各施工班组的施工入数又不同，使同一施工过程在各施工段上或各施工过程在同一施工段上的流水节拍无规律性，这是需要组织无节奏专业流水。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]