[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156745":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156745,817,1,"单选题","在工程网络计划中，关键工作是指网络计划中（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","总时差为零的工作",false,{"key":16,"text":17,"correct":18},"B","总时差最小的工作",true,{"key":20,"text":21,"correct":14},"C","自由时差为零的工作",{"key":23,"text":24,"correct":14},"D","自由时差最小的工作","工程网络计划中，关键工作是指网络计划中总时差最小的工作。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]