[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156733":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1156733,817,1,"单选题","某施工项目进行成本管理，采取了多项措施，其中实行项目经理责任制、编制工作流程图等措施属于施工成本管理的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",true,{"key":16,"text":17,"correct":18},"B","技术措施",false,{"key":20,"text":21,"correct":18},"C","经济措施",{"key":23,"text":24,"correct":18},"D","合同措施","组织措施，分析由于组织的原因而影响项目目标实现的问题，并采取相应的措施，如调整项目组织结构、任务分工、管理职能分工、工作流程组织和项目管理班子人员等。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]