[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156732,817,1,"单选题","某施工项目部决定将原来的横道图进度计划改为网络进度计划进行进度控制，以避免工作之间出现不协调情况。该项进度控制措施属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":18},"B","管理措施",true,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","技术措施","管理措施（包括合同措施），分析由于管理的原因而影响项目目标实现的问题，并采取相应的措施，如调整进度管理的方法和手段，改变施工管理和强化合同管理等。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]