[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156729,817,1,"单选题","施工组织总设计包括如下工作：①计算主要工种工程的工程量；②编制施工总进度计划；③编制资源需求量计划；④拟订施工方案。其正确的工作排序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","①②③④",false,{"key":16,"text":17,"correct":18},"B","①④②③",true,{"key":20,"text":21,"correct":14},"C","①③②④",{"key":23,"text":24,"correct":14},"D","④①②③","施工组织总设计的顺序：拟订施工方案、编制施工总进度计划、编制资源需求量计划。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]