[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156720,817,1,"单选题","项目目标动态控制的核心是在项目实施的过程中定期地进行（ ）的比较。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目目标计划值和偏差值",false,{"key":16,"text":17,"correct":14},"B","项目目标实际值和偏差值",{"key":19,"text":20,"correct":21},"C","项目目标计划值和实际值",true,{"key":23,"text":24,"correct":14},"D","项目目标当期值和上-期值","项目目标动态控制的核心是在项目实施的过程中定期地进行项目目标计划值和实际值的比较。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]