[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156712":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156712,817,1,"单选题","当一个施工段上所需完成的劳动量（工日数）或机械台班量（台班数）和每天的工作班数固定不变，增加班组的入数或机械台班数，流水节拍（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","变大",false,{"key":16,"text":17,"correct":18},"B","不变",true,{"key":20,"text":21,"correct":14},"C","不能确定",{"key":23,"text":24,"correct":14},"D","变小","当一个施工段上所需完成的劳动量（工日数）或机械台班量（台班数）和每天的工作班数固定不变，增加班组的入数或机械台班数，流水节拍不变。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]