[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1156703,817,1,"单选题","根据《建设工程项目管理规范》GB\u002FT50326-2006，项目管理实施规划应由（ ）组织编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目技术负责人",false,{"key":16,"text":17,"correct":14},"B","企业生产负责人",{"key":19,"text":20,"correct":14},"C","企业技术负责人",{"key":22,"text":23,"correct":24},"D","项目经理",true,"根据《建设工程项目管理规范》GB\u002FT50326-2006，项目管理实施规划应由项目经理组织编制。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]