[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156702":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156702,817,1,"单选题","下列进度控制措施中，属于管理措施的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编制工程资源需求计划",false,{"key":16,"text":17,"correct":18},"B","应用互联网进行进度控制",true,{"key":20,"text":21,"correct":14},"C","制订进度控制工作流程",{"key":23,"text":24,"correct":14},"D","选择先进的施工技术","管理措施（包括合同措施），分析由于管理的原因而影响项目目标实现的问题，并采取相应的措施，如调整进度管理的方法和手段，改变施工管理和强化合同管理等。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]