[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156691":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156691,817,1,"单选题","下列说法错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在正式施工时，应该首先进行全场性工程的施工",false,{"key":16,"text":17,"correct":14},"B","在安排架设电线、敷设管网和修筑公路的施工程序时，场外需要由远而近，先主干后分支",{"key":19,"text":20,"correct":21},"C","在安排架设电线、敷设管网和修筑公路的施工程序时，应先场内后场外",true,{"key":23,"text":24,"correct":14},"D","排水工程要先下游后上游","在正式施工时，应该首先进行全场性工程的施工；在安排架设电线、敷设管网、修建铁路和修筑公路的施工程序时，应先场外后场内；场外需要由远而近，先主干后分支；排水工程要先下游后上游。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]