[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1156687,817,1,"单选题","运用动态控制原理控制建设工程项目进度时，第一步工作是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","收集工程进度实际值",false,{"key":16,"text":17,"correct":14},"B","进行进度目标的调整",{"key":19,"text":20,"correct":14},"C","进行工程进度的计划值和实际值的比较",{"key":22,"text":23,"correct":24},"D","进行项目目标分解，确定目标控制的计划值",true,"运用动态控制原理控制进度的步骤如下：第一步，工程进度目标的逐层分解。第二步，在项目实施过程中对工程进度目标进行动态跟踪和控制。第三步，如有必要，则调整工程进度目标。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]