[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1156659,817,1,"单选题","根据预制桩入土受力方式分为打入式和（ ）两种。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","动力压桩式",false,{"key":16,"text":17,"correct":18},"B","静力压桩式",true,{"key":20,"text":21,"correct":14},"C","弹力压桩式",{"key":23,"text":24,"correct":14},"D","阻力压桩式","根据预制桩入土受力方式分为打入式和静力压桩式两种。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]