[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1156628,817,1,"单选题","基坑（槽）采用井点降水，水位应降至基坑（槽）底以下（ ）mm，以利于土方开挖。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","100",false,{"key":16,"text":17,"correct":14},"B","300",{"key":19,"text":20,"correct":21},"C","500",true,{"key":23,"text":24,"correct":14},"D","700","基坑（槽）采用井点降水，水位应降至基坑（槽）底以下500mm，以利于土方开挖。",{"id":6,"name":27,"category":28,"favorite":29},"(标准员)基础知识","建筑工程",0]