[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1156401":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1156401,808,2,"多选题","成本控制目标的确定方法一般包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程量法",false,{"key":16,"text":17,"correct":14},"B","建筑面积法",{"key":19,"text":20,"correct":21},"C","计划指标分解法",true,{"key":23,"text":24,"correct":21},"D","定额法",{"key":26,"text":27,"correct":21},"E","预算法","CDE","成本控制首先要明确控制标准。成本的控制标准或目标，是对各项费用支出和资源消耗规定的数量界限，是进行成本控制和考评的直接依据。实务中，常用的控制标准有成本预算和消耗定额等，它们是成本控制的准绳，也是分析和评价的依据。成本控制目标的确定一般可以按计划指标分解法、定额法、预算法三种方法确定。",{"id":6,"name":31,"category":32,"favorite":33},"物业经营管理","建筑工程",0]