[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1155810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1155810,807,2,"多选题","施工质量控制包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","事前质量控制",true,{"key":16,"text":17,"correct":18},"B","全面质量控制",false,{"key":20,"text":21,"correct":14},"C","事中质量控制",{"key":23,"text":24,"correct":18},"D","分步质量控制",{"key":26,"text":27,"correct":14},"E","事后质量控制","ACE","施工质量控制应贯彻全面全过程质量管理的思想，运用动态控制原理，进行质量的事前控制、事中控制和事后控制。事前质量控制，即在正式施工前进行的事前主动质量控制，事中质量控制，指在施工质量形成过程中，对影响施工质量的各种因素进行全面的动态控制，事后质量控制，旨在使不合格的工序或最终产品不流入下道工序、不进入市场。",{"id":6,"name":31,"category":32,"favorite":33},"物业管理综合能力","建筑工程",0]