[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1155593":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1155593,807,2,"多选题","管理控制工作的一般程序包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建立控制标准",true,{"key":16,"text":17,"correct":14},"B","运用检测手段进行观察、测度和衡量",{"key":19,"text":20,"correct":14},"C","分析差异产生的原因",{"key":22,"text":23,"correct":14},"D","采取矫正措施",{"key":25,"text":26,"correct":27},"E","修改控制标准",false,"ABCD","控制首先要有一个控制的依据或标准，这往往是计划中所规定的，其次，要运用各种监测手段对进行中的活动进行观察、测度和衡量，再次，对观测到的、测度到的情况和数据要与计划规定的标准进行比较，发现是否存在差异，最后，如衡量结果与标准之间存在差异，就采取各种措施和方法加以解决。",{"id":6,"name":31,"category":32,"favorite":33},"物业管理综合能力","建筑工程",0]