[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1155489":3},{"question":4,"library":25},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":24},1155489,807,1,"单选题","建设单位应当在工程竣工验收()个工作日前将验收的时间、地点及验收组名单书面通知负责监督该工程的工程质量监督机构。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":14},"B","6",{"key":19,"text":20,"correct":21},"C","7",true,{"key":23,"text":16,"correct":14},"D","建设单位应当在竣工验收了个工作日前将验收的时间、地点及验收组名单书面通知负责监督该工程质量监督机构。",{"id":6,"name":26,"category":27,"favorite":28},"物业管理综合能力","建筑工程",0]