[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1154972":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1154972,806,2,"多选题","在物业管理方案中，整体工作计划的制订大体可以分成三个阶段，即筹备期、交接期和正常运作期。其中交接期的工作计划内容不包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制订《临时管理规约》",false,{"key":16,"text":17,"correct":18},"B","物业管理供应商的评审和确定",true,{"key":20,"text":21,"correct":14},"C","建筑物本体和设备资料的接收建档",{"key":23,"text":24,"correct":18},"D","制订交接验收计划及做好相关准备",{"key":26,"text":27,"correct":14},"E","签订《前期物业管理协议》或《物业管理委托合同》","BD","",{"id":6,"name":31,"category":32,"favorite":33},"物业管理实务","建筑工程",0]