[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1154970":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1154970,806,2,"多选题","制订计划过程中，要考虑物业管理方案实施不同阶段的工作重点、项目、内容、时间要求等因素，可采用（ ）等表现方式。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","表格法",true,{"key":16,"text":17,"correct":18},"B","横道图法",false,{"key":20,"text":21,"correct":18},"C","曲线法",{"key":23,"text":24,"correct":18},"D","直线法",{"key":26,"text":27,"correct":14},"E","图表法","AE","",{"id":6,"name":31,"category":32,"favorite":33},"物业管理实务","建筑工程",0]