[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1153744":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1153744,805,1,"单选题","非出售的新建物业项目通过招投标方式选择前期物业服务企业的，招标人应当在交付使用前()日完成招投标工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","30",{"key":19,"text":20,"correct":14},"C","60",{"key":22,"text":23,"correct":24},"D","90",true,"通过招投标方式选择物业服务企业的，招标人应当按照以下规定时限完成物业管理招标投标工作：①新建现售商品房项目应当在现售前30日完成，②预售商品房项目应当在职得《商品房预售许可证》之前完成，③非出售的新建物业项目应当在交付使用前90日完成。",{"id":6,"name":27,"category":28,"favorite":29},"物业管理基本制度与政策","建筑工程",0]