[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1153255":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1153255,804,2,"多选题","设备通电前的检查应包括( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","插好架内保险和分保险",false,{"key":16,"text":17,"correct":18},"B","机架和机框内部应清洁，查看有无焊锡、芯线头、脱落的紧固件或其他异物",true,{"key":20,"text":21,"correct":18},"C","架内无断线混线，开关、旋钮、继电器、印刷电路板齐全，插接牢固",{"key":23,"text":24,"correct":18},"D","开关预置位置符合说明书要求",{"key":26,"text":27,"correct":18},"E","各接线器、连接电缆插头连接应正确、牢固、可靠","BCDE","通电前检查 1.卸下架内保险和分保险，检查架内电源线连接是否正确、牢固、松动。 2. 在机架电源输人端应检查电源电压、极性、相序。 3. 机架和机框内部应清沽，清除焊锡(渣)、芯线头、脱落的紧固件或其他异物。 4. 架内无断线混线，开关、旋钮、继电器、印刷电路板齐全，插接牢固。 5. 开关预置位置应符合说明书规定。 6. 各接线器、连接电缆插头连接应正确、牢固、可靠。 7. 接线端子插接应正确无误。",{"id":6,"name":31,"category":32,"favorite":33},"一建通信与广电工程实务","建筑工程",0]