[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1153089":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1153089,804,2,"多选题","演播室灯光施工中调光系统的调试的最后一步是打开所有负载的65％～85％并保持1．5～2h，检测( )，直至调光系统所有设备全部正常工作。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","电源电压的波动情况",true,{"key":16,"text":17,"correct":14},"B","空气开关的表面温度",{"key":19,"text":20,"correct":14},"C","调光柜的运行情况",{"key":22,"text":23,"correct":14},"D","散热系统的运行情况",{"key":25,"text":26,"correct":27},"E","测试三相电源之间及每相对零、对地的绝缘电阻",false,"ABCD","测试三相电源之间及每相对零、对地的绝缘电阻是针对电源的安全进行的，不直接影响调光系统的性能。",{"id":6,"name":31,"category":32,"favorite":33},"一建通信与广电工程实务","建筑工程",0]