[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1152526":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1152526,804,1,"单选题","通信机房拆除旧设备时应先拆除( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","光纤",false,{"key":16,"text":17,"correct":14},"B","信号线",{"key":19,"text":20,"correct":21},"C","电源线",true,{"key":23,"text":24,"correct":14},"D","接地线","拆除过程应遵循的原则为:先拆除备用电路，后拆除主用电路;先拆除支路，后拆除群路;先拆除线缆，后拆除设备;先拆除设备，后拆除走线架;先拆除电源线后拆除信号线。",{"id":6,"name":27,"category":28,"favorite":29},"一建通信与广电工程实务","建筑工程",0]