[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1152287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1152287,804,1,"单选题","演播室灯光施工中调光系统的调试的最后一步是打开所有负载的( )并保持1．5～2h，检测电源电压的波动情况，电力电缆的电流和温度，空气开关的表面温度，调光柜的运行情况及散热系统，直至调光系统所有设备全部正常工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","55％～60％",false,{"key":16,"text":17,"correct":18},"B","65％～85％",true,{"key":20,"text":21,"correct":14},"C","90％～95％",{"key":23,"text":24,"correct":14},"D","100％","",{"id":6,"name":27,"category":28,"favorite":29},"一建通信与广电工程实务","建筑工程",0]