[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151997":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151997,803,2,"多选题","根据《水工建筑物地下开挖工程施工规范》SL378-2007，特大断面洞室（或大断面隧洞）采用先拱后墙法施工时，拱脚下部岩石开挖应符合的要求有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","拱脚线的最低点至下部开挖面的距离，不宜小于1.5m",true,{"key":16,"text":17,"correct":18},"B","拱脚线的最低点至下部开挖面的距离，不宜小于2.5m",false,{"key":20,"text":21,"correct":14},"C","顶拱混凝土衬砌强度不应低于设计强度的75%",{"key":23,"text":24,"correct":18},"D","顶拱混凝土衬砌强度不应低于设计强度的65%",{"key":26,"text":27,"correct":18},"E","顶拱混凝土衬砌强度不应低于设计强度的55%","AC","2020版教材P394 \u002F 2019版教材P393 5.5.5当特大断面洞室设有拱座，采用先拱后墙法开挖时，应注意保护和加固拱座岩体。拱脚下部的岩体开挖，应符合下列条件：1拱脚下部开挖面至拱脚线最低点的距离不应小于1.5m。2顶拱混凝土衬砌强度不应低于设计强度的75%。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]