[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151956":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151956,803,2,"多选题","申办下序单元工程的开工签证，承建单位必须凭上序单元工程的（ ）进行申办。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","开工签证",false,{"key":16,"text":17,"correct":14},"B","完工报告",{"key":19,"text":20,"correct":21},"C","施工质量终检合格证",true,{"key":23,"text":24,"correct":21},"D","质量评定表",{"key":26,"text":27,"correct":14},"E","施工作业措施计划","CD","2020版教材P331 \u002F 2019版教材P330 （3）单元工程开工申请。单元工程开工，承建单位必须按工程承建合同文件和相应的监理细则文件要求，向监理机构申报单元工程开工签证。下序单元工程的开工，由承建单位凭上序施工质量终检合格证和单元工程质量评定表向监理机构申办开工签证。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]