[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151954":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1151954,803,2,"多选题","监理机构施工阶段进度控制的主要任务包含（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","控制性总进度计划的审批",false,{"key":16,"text":17,"correct":18},"B","协助业主编制工程控制性总进度计划",true,{"key":20,"text":21,"correct":18},"C","审查承建单位报送的施工进度计划",{"key":23,"text":24,"correct":18},"D","依据工程监理合同，向业主编报进度报表",{"key":26,"text":27,"correct":18},"E","向业主提供关于施工进度的建议及分析报告","BCDE","2020版教材P331 \u002F 2019版教材P330 水力发电工程监理进度控制的内容，监理机构施工阶段进度控制的主要任务（1）协助业主编制工程控制性总进度计划。（2）审查承建单位报送的施工进度计划。（3）对工程进展及进度实施过程进行控制。（4）按合同文件规定受理承建单位申报的工程延期索赔申请。（5）向业主提供关于施工进度的建议及分析报告。（6）依据工程监理合同规定，向业主编报进度报表。",{"id":6,"name":31,"category":32,"favorite":33},"一建水利水电工程实务","建筑工程",0]